Math, asked by arc632000, 1 month ago

A and B did a piece of work in 10 days b and c in 15 days and c and a in 20 days they all worked together for 6 days and then A leaves,and b and c goes on for 4 days more .if b leaves how long will c take to complete the work​

Answers

Answered by bradlamar691
1

Answer:

10 days

Step-by-step explanation:

A and B do a piece of work in 10 days

⇒Work Done By A and B in One Day (A+B) = \frac{1}{10}      ----- (1)

B and C do a piece of work in 15 days

⇒Work Done By B and C in One Day (B+C) = \frac{1}{15}       ------(2)

A and C can do a piece of work in 20 days

⇒Work Done By A and C in One Day (A+C) = \frac{1}{20}                     ------(3)

Work Done by A, B, and C in One Day = (A+B+C)

Adding the three equations (1)+(2)+(3)

A+B+B+C+C+A = \frac{1}{10} + \frac{1}{15} +\frac{1}{20}

2A+2B+2C = \frac{6 + 4 + 3}{60}

2(A+B+C) = \frac{13}{60}

A+B+C = \frac{13}{120}

A, B, and C worked together for 6 days

⇒Work Done By A, B, and C in 6 days = \frac{13}{120} *6 = \frac{13}{20}

Work Left After A Leaves = 1 - \frac{13}{20} = \frac{7}{20}

B, and C Work together for 4 days

⇒Work Done by B and C in 4 days = \frac{1}{15} *4 = \frac{4}{15}

Work Left after B leaves = \frac{7}{20}  - \frac{4}{15} = \frac{21-16}{60} = \frac{5}{60} = \frac{1}{12}

Work done by C in One Day = C

We know that A+B+C=\frac{13}{120} and A+B = \frac{1}{10}

Substituting the values

\frac{1}{10} +C=\frac{13}{120}

C = \frac{13-12}{120}

C = \frac{1}{120}

⇒Work done by C in One Day = \frac{1}{120}

No Of days taken to finish the job by C = x

\frac{1}{120} * x = \frac{1}{12}

x = 10 days

C takes 10 days to finish the job

Similar questions