A and B do a piece of work in 10 days and 6 days respectively. They work together for 2 days and B leaves the work .In how many days A will finish the remaining work...
Who'll give right ans I'll mark him/her as Brainlist
Answers
Answered by
0
Step-by-step explanation:
- A=10
- B=6
- A+B=8 days
- if B leaves in two days A will finish the work in 6 days.
- mark as brainliest