A and b do a work in 30 days b and c do a work in 24 days a and c do a work in 20 days . They all together do a work in 10 days when b and c leave .Then a takes how many days ?
Answers
Answered by
0
A and B can do a piece of work in 30 days, while B and C can do the same work 24 days, and A and C can do it in 20 days. They work together for 10 days before B and C leave. How many days more will A take to finish the work?
Answer
8
Follow
Request
More
7 ANSWERS

Gauri Shanker, 96.7%iler in CAT, AIR under 100 twice in SSC CGL.
Answered Jun 14
Let the work is 120 units. #just a trick, you can assume anything #
Let a, b and c be the works done by them per day.
As per the question
a+b = 120/30 = 4 units/day.
Similarly b+c = 5
c+a = 6
Solving these, we get a= 2.5, b = 1.5, c=3.5.
In 10 days, they'll do 10*(7.5) = 75.
Remaining work = 120–75= 45
Then A will do 45 units in 45/2.5 = 18 days
Answer
8
Follow
Request
More
7 ANSWERS

Gauri Shanker, 96.7%iler in CAT, AIR under 100 twice in SSC CGL.
Answered Jun 14
Let the work is 120 units. #just a trick, you can assume anything #
Let a, b and c be the works done by them per day.
As per the question
a+b = 120/30 = 4 units/day.
Similarly b+c = 5
c+a = 6
Solving these, we get a= 2.5, b = 1.5, c=3.5.
In 10 days, they'll do 10*(7.5) = 75.
Remaining work = 120–75= 45
Then A will do 45 units in 45/2.5 = 18 days