a and b do a work in 30 days while b and c do it in 24 days and c and a do it in 20 days how many days will a take to complete the whole work
Answers
Answered by
0
one days work of :
a+b = 1/30
b+c = 1/24
c+a = 1/20
then
2a+2b+2c = 1/30 +1/24+ 1/20 = 1/8
a+b+c = 1/16
a = a+b+c -a
= 1/16 - 1/24
= 1/48
a alone can finish the work in 48days