Math, asked by balistargupta95, 6 months ago

A and B finish a work in 5 and 6 days respectively. they start together and earn 2200rp. find the B labour charge​

Answers

Answered by mohithmanjunath1110
0

Answer:

A & B working together do work in 6 days.

A takes 5 days less than B.

Let B takes x

A=x−5

1  / x  +   1 / x- 5   =   1/6

x−5+x   /  x^2 -   5x = 1/6

12x−30=x ^2-5x

x^2-17x+30=0

x ^2 −15x−2x+30=0

x(x−15)−2(x−15)=0

(x−2)(x−15)=0

⇒x=2  or  x=15

As, x<5     so x=15

then A=10 days &B=15 days

Hence, the answer is 10,15days.

hope it helps

tq.........../////////

Step-by-step explanation: