Math, asked by milo35, 3 months ago

A and B separately do a work in 10 and 15 days respectively. They worked together fo some days and then A completed the remaining work in 5 days. For how many days had A and B worked together?

Answers

Answered by jimin084
5

follow me..............

Attachments:
Similar questions