 A and B start working together, after some days A left the work and the whole work completed in 9days.Find after how many days did A left, if A and B completes the work in 10 &15 days respectively.​

Answers

Answered by jsanthoshjoshhh
0

Answer:

After 4 days

Step-by-step explanation:

A=10 days

B=15 days

suppose work will be 60 units A can do 6units /day

B can do it 4 units /day

A will leave some days but B will do it entire work was done so he work for 9 days.

B can do 4 units/day for 9 days he can do 36 units

so the remaining work will be done by A.

Remaining work 60-36=24

A can do it 6 units per day, for 24 units he will take 4 Days

so A  left the work after 4 days.

Hope you understand