Math, asked by gaganprakash1, 7 months ago

A and B together, B and C together, and A and C together can do a certain piece of work in x, x+6 and 63/2 days , respectively. A,B and C together can complete the work in 24 days. A,B and C start the work together and after 12 day A left the job and 24 days before the complition on the work C also left. In how many day the work is completed?

Answers

Answered by amitnrw
0

Given :  A and B together, B and C together, and A and C together can do a certain piece of work in x, x+6 and 63/2 days , respectively

To find :  In how many day the work is completed

Solution:

Let say A , B , & C complete work in  A , B & C  Days respectively

Hence their 1 day work are 1/A , 1/B & 1/C

1/A + 1/B = 1/x  

1/B + 1/C = 1/(x + 6  )

1/A + 1/C  =  2/63

Adding all 2 ( 1/A + 1/B + 1/C)  = 1/x  + 1/(x + 6)  + 2/63

1/A + 1/B + 1/C = 1/24

=> 2(1/24) = 1/x  + 1/(x + 6)  + 2/63

=> 1/12 = 1/x  + 1/(x + 6)  + 2/63

=>  1/x  + 1/(x + 6)  = 1/12  - 2/63

=> (2x  + 6)/x(x + 6)  = (21  - 8)/252

=>   504x + 1512  = 13x²  + 78x

=>  13x²  -426x   - 1512 = 0

=> 13x²  -  468x  + 42x - 1512 = 0

=> 13x(x - 36) + 42(x - 36) = 0

=> x = 36

1/A + 1/B = 1/36      1/B + 1/C = 1/42     1/A + 1/C  =  2/63

1/A + 1/B + 1/C = 1/24

=> 1/C = 1/24 - 1/36   = (3 - 2)/72 = 1/72

=> C  =  72

1/A = 1/24 - 1/42  =  (7 - 4)/168   = 3/168 = 1/56

=> A = 56

1/A + 1/B = 1/36   =>  1/B = 1/36 - 1/56  = 5/504

=> B =  100.8  

Work Done in 12 Days  = 12 (1/24)  =  1/2

B Worked alone for 24 Days after C left

Work done by B = 24 (5/504)  = 5/21

Work done by B & C  = 1 - 1/2 - 5/21  =   1/2 - 5/21

= (21 - 10)/42

= 11/42

=> B & C worked for 11 Days

Total Days Worked =  12 + 11  +  24

= 47

in 47 Days Work completed

Learn more:

with P starting the work, working on alternate days P and Q can ...

https://brainly.in/question/12303996

A and B can do a piece of work in 12 days; A,B and C all working ...

https://brainly.in/question/7839397?source=aid17352661

A takes 6 days less than B to do a work . If both A and B working ...

https://brainly.in/question/7656573

Answered by bestwriters
0

The work was completed in 47 days.

Step-by-step explanation:

From question, we have that,

1/A + 1/B = 1/x → (equation 1)

1/B + 1/C = 1/(x + 6)  → (equation 2)

1/A + 1/C = 2/63 → (equation 3)

On adding equation 1, 2 and 3, we get,

2(1/A + 1/B + 1/C) = 1/x + 1/(x + 6) + 2/63

From question, A, B and C together can complete the work in 24 days.

2(1/24) = 1/x + 1/(x + 6) + 2/63

1/12 = 1/x + 1/(x + 6) + 2/63

1/x + 1/(x + 6) = 1/12 - 2/63

(2x  + 6)/(x(x + 6)) = 13/252

252(2x  + 6) = 13(x(x + 6))

504x + 1512 = 13x² + 78x

13x² - 426x - 1512 = 0

13x² - 468x + 42x - 1512 = 0

(13x + 42)(x - 36) = 0

The negative value is not considered.

∴ x = 36

Now, the value of C is:

1/36 + 1/C = 1/24 ⇒ 1/C = 1/24 - /36

∴ C = 72

Now, the value of B is:

1/B + 2/63 = 1/24 ⇒ 1/B = 1/24 - 2/63

∴ B = 100.8

Now, the value of A is:

1/A + 1/42 = 1/36 ⇒ 1/A = 1/36 - 1/42

∴ A = 56

From question, the work done by A in 12 days.

⇒ 24 (5/504) = 5/21

From question, the number of days worked by B and C.

⇒ (21 - 10)/42  = 11/42

The number of days worked is:

∴ D = 11 + 12 + 24 = 47 days

Similar questions