Math, asked by rishmitabiswas0, 2 days ago

A and B together can build a wall in 10 days. B and C working together can do it in 15 days. C and A together can do it in 12 days. How long will they take to finish the work altogether also find no. of days taken by each one working alone​

Answers

Answered by ritishachandra09
0

Answer:

BandC will take 15 days each,B will take 20 days C on the other hand will take 25 days ,A and C will both take 18 days each.

Answered by apoorva12389
1

Answer:

work done by A and B together in 1 day =

1/10

work done by B and C together in 1 day =

1/15

work done by A and C together in 1 day =

1/12

2(work done by A, B and C) in 1 day

= (1/10+ 1/15+ 1/12)

= 6+4+5/60

= 15/60= 1/4 =

work done by A, B and C=1/4*2 = 1/8 Time taken by them all together = 8 days