A and b together can complete a particular task in 4 days. If a alone can complete the same task in 6 days, how many days will b take to complete the task if he works alone?
Answers
Answered by
22
Answer:
Step-by-step explanation:
Answered by
11
The number of days required by B to complete the work alone is 12 days.
- A and B can complete a task in 4 days.
Therefore, part of the task A and B can do in one day is 1/4.
- A alone can do a piece of work in 6 days.
Work done by A alone in one day is 1/6.
- Let number of days required for B to complete the work alone be x days.
Work done by B alone in one day is 1/x.
- Therefore, work done by both of them together in one day is equal to sum of both A and B working alone in one day.
1/4 = 1/6 + 1/x
1/x = 1/4 - 1/6
1/x = 2/24
x = 12
- The number of days required for B to complete the work lone be 12 days.
Similar questions