Math, asked by lsimhachalam32, 9 months ago

A and B together can complete a piece of work in 4 days. A alone can complete the
same work in 12 days. In how many days, can B alone complete the work?​

Answers

Answered by tyrbylent
1

Answer:

6 days

Step-by-step explanation:

Efficiency of A and B together is \frac{1}{4}

Efficiency of A is \frac{1}{12}

Efficiency of B is \frac{1}{x}

\frac{1}{x} + \frac{1}{12} = \frac{1}{4}

\frac{1}{x} = \frac{1}{4} - \frac{1}{12}

\frac{1}{x} = \frac{3-1}{12}

\frac{1}{x} = \frac{2}{12}

\frac{1}{x} = \frac{1}{6}

x = 6 days