A and b together can complete a work in 16 days. A having worked for 8 days, b completes the work in 32 days. In how many days can b alone finish the whole work?
Answers
Answered by
18
Solution :
A and B together can finish a piece of work in 16 days. A having worked for 8 days, B finishes the remaining work alone in 32 days.
The days shall be B finish the whole work alone.
Let A's work in 1 day = r
Let B's work in 1 day = m
We know that total work = 1
A/q
&
∴ The B's finish the whole work alone in = 48 days .
Answered by
10
Answer:
Step-by-step explanation:
This question is equivalent to saying A & B work together for 16 days completing 16/30 part of work.
Remaining 14/30 part of work is completed by B alone in 44 - 16 = 28 days.
=> B alone can complete work in 28 x 30/14 = 48 days.
Similar questions