A and B together can complete a work in 20 days while A is 25% more efficient than B, then find in how many days the work will be complete if they work on alternate days starting with A?
Answers
Answered by
0
Answer:
63 days
Step-by-step explanation:
Answered by
2
They will complete the work in 30 days.
Step-by-step explanation:
Let us assume that A can complete in x days.
As A is 25% more efficient than B, then B will complete the job in days.
Now, together they will do in one day part of the job.
So, they will complete the job together in days.
Hence, given that
⇒ x = 27 days.
Therefore, A can do the job in 27 days alone and B will do the job in (27 × 1.25) =33.75 days alone.
Now, if they work on alternate days starting with A, then after 2 days they will complete part of the job.
So, they will complete the work in days. (Answer)
Similar questions