A and B together can complete a work in
3 days. They start together but after 2 days, B
left the work. If the work is completed after
two more days, B alone could do the work in
Answers
Answered by
3
Answer:
1st Method:
(A+B)'s one day's work = 1/3 part;
(A+B) works 2 days together = 2/3 part;
Remaining work = 1-(2/3) = 1/3 part;
1/3 part of work is completed by A in two days;
Hence, one day's work of A = 1/6;
Then, one day's work of B = 1/3-1/6=1/6;
So, B alone can complete the whole work in 6 days.
2nd method:
(A+B)'s one day's % work = 100/3 = 33.3%
Work completed in 2 days = 66.6%
Remaining work = 33.4%;
One day's % work of A = 33.4/2 = 16.7%;
One day's work of B = 33.3 - 16.7 = 16.7%;
B alone can complete the work in,
= 100/16.7 = 6 days.
Answered by
0
Answer:
6 days
Step-by-step explanation:
(A + B) ×3 = B×2 + 4 × A
A worked for (2+2 = 4days ) & B Worked for 2 days .
3A + 3B = 2B + 4A => A = B => A/B = 1/1
T.W = (1+1)×3 =6 units
B alone = 6/1 = 6 days
Similar questions
Math,
4 months ago
Social Sciences,
4 months ago
Hindi,
4 months ago
Biology,
8 months ago
Math,
1 year ago