A and B together can do a pieace
of work in 10 days. but à
alone can do it in 15 days. How
Many days would B alone take
to do the same work?
Answers
Answered by
0
Answer:
Here is ur answer:-
work done by A and B in one day= 1/10
work done by A in one day=1/15
work done by B in one day=1/10 - 1/15
=30 days