A and b together can do a piece of work 12 days.which b and c together can do in 16 days.after a has been working it for 5 days and b for 7 days,c finishes it in 13 days.in how many days c alone will do the work give correct answer with working
Answers
Answered by
1
Assuming everybody works at constant rate and independent from each other.
When A works for 5 days and B works for 7 days, we can conclude that A and B work together for 5 days and B works alone for 2 days. And
Work Rate(A+B) = 1/12 (work/day)
Thus, Work is done by A and B for 5 days together = 5 days x 1/12 (work/day) = 5/12 work
When B works for 7-5 = 2 days and C works for 13 day, we can conclude that B and C work together for 2 days and C work alone for 13 - 2 = 11 days.
Work Rate(B+C) = 1/16 (work/day)
Thus, Work is done by B and C for 2 days = 2 days x 1/16 (work/day) = 1/8 work
The remaining job = 1 - 5/12 - 1/8 = (24 - 10 - 3)/24 = 11/24 work
C can finish this part of work within 11 days. Therefore, the work rate for C = 11/24 (work) x 1/11(1/day) = 1/24 (work/day)
Or C can finish one work in = 24 days
When A works for 5 days and B works for 7 days, we can conclude that A and B work together for 5 days and B works alone for 2 days. And
Work Rate(A+B) = 1/12 (work/day)
Thus, Work is done by A and B for 5 days together = 5 days x 1/12 (work/day) = 5/12 work
When B works for 7-5 = 2 days and C works for 13 day, we can conclude that B and C work together for 2 days and C work alone for 13 - 2 = 11 days.
Work Rate(B+C) = 1/16 (work/day)
Thus, Work is done by B and C for 2 days = 2 days x 1/16 (work/day) = 1/8 work
The remaining job = 1 - 5/12 - 1/8 = (24 - 10 - 3)/24 = 11/24 work
C can finish this part of work within 11 days. Therefore, the work rate for C = 11/24 (work) x 1/11(1/day) = 1/24 (work/day)
Or C can finish one work in = 24 days
gopal5426:
okk
Similar questions
History,
7 months ago
Environmental Sciences,
7 months ago
Computer Science,
7 months ago
Economy,
1 year ago
English,
1 year ago
English,
1 year ago