A and B together can do a piece of work in 10 days. If A alone will take 12 days to finish the work, will B take to finish the work?​

Answers

Answered by shamanarang814
1

Answer:

A and B = 10 days

in one day A and B can do job = 1/10

A alone =12 days

A can do work alone in 1 day = 1/12

B alone can do work in = 1/10-1/12

= 6-5/60

= 1/60

:: B alone can do work in 60 days