A and B together can do a piece of work in 12 days and A alone can do it in 24 days . How long will B take to complete the work ? Answer in step by step
Answers
Answered by
5
Answer :
B can alone do the work on 24 days.
Step-by-step explanation :
To Find,
- How long will B take to complete the work ?
Solution,
Given that,
- A and B together can do a piece of work in 12 days
- A alone can do it in 24 days
Therefore,
( A + B )'s 1 day's work = 1/12
A's 1 day's work = 1/24
B's 1 day's work = [ ( A + B )'s 1 day's work ] - ( A's 1 day's work )
» 1/12 - 1/24
» ( 2 × 1 ) - ( 1 × 1 ) / 24
» 2 - 1 / 24
» 1/24
Hence, B can alone do the work on 24 days.