A and B together can do a piece of work in 16 days and A alone can do it in 48 days.
How long will B take to complete the work?
Answers
Answered by
11
Hence the correct answer is 24days
Refer to the attachment for details...
Hope this helps you
have a great day ❤️☑️⬆️
Attachments:
Answered by
115
So in 1 day they can do 1/16 of the work in 1 day. Similarly, A alone will do 1/24 of the work in 1 day. Therefore, B alone can do 1/16 - 1/24 = 1/48 of the work in 1 day, which means that B alone can do the complete work in 48 days.