Math, asked by kanhakirteemaabbsr, 7 months ago

A and B together can do a piece of work in 20 days, B and C together can do it in 15 days,
C and A together can do it in 12 days.
(i) How long will they take to finish the work, working all together?
(ii) How long would it take to do the same work?

The answer is:
i) 10 days
ii) A=30 days
B=60 days
C=20 days

Please give right answers with explanation and process

Correct answers will be marked as brainliest ​

Answers

Answered by shikshajaiswal8e
2

Answer:

Always go with the LCM method, as answer can be calculated while the first reading of the question as the calculation involves integers instead of fractions and they are easily handled.

LCM(12,15,20)=60

Now this 60 units can be treated as the total work and we will now calculate the one day work

One day work of A and B = 60/12 = 5 units

One day work of B and C = 60/15 = 4 units

One day work of C and A = 60/20= 3 units

Now if we add all three we get:-

2(A+B+C)=12 units

So one day work of A, B and C put together is 12/2 = 6 units

To find one day work of A:-

One day work of A, B and C together minus one day work of B and C, that is 6–4=2 units

If the total work is of 60 units and the one day work of A is 2 unit, then alone A needs 60/2 = 30 days to finish the work.

Answered by Raunakchandrakar
0

Step-by-step explanation:

Time taken by

A

and

B

to complete a unit of work

=

12

days

Therefore, work done by

A

and

B

in

1

day

=

1

12

units of work

Similarly,

Work done by

B

and

C

is

1

day

=

1

15

units of work

Work done by

A

and

C

in

1

day

=

1

20

units of work

Therefore, total work done by

A

,

B

and

C

=

1

2

×

(

1

12

+

1

15

+

1

20

)

LCM of

12

,

15

and

20

is

60

=

1

2

×

(

1

×

5

+

1

×

4

+

1

×

3

60

)

=

1

2

×

(

12

60

)

=

1

10

units of work

Therefore, work done by

A

alone in

1

day

=

Total work done

Work done by

B

and

C

=

1

10

1

15

=

1

×

3

1

×

2

30

=

1

30

units of work

Hence, time taken by

A

to complete a unit of work

=

30

days

Similar questions