Math, asked by ya852620, 1 month ago

A and B together can do a piece of work in 4 days. If they work separately, the
time taken by B to do the work would be 6 days more than that taken by A.
In how many days can A alone do the work?​

Answers

Answered by navneetkumarmaurya65
0

Step-by-step explanation:

nhzhzhzhshshzjajajzhzhhGG

Answered by ranujhanvi
0

Answer:

(A+B)'s 1 day's work = 1/4

A's 1 day's work = 1/12

B's 1 day's work =( 1/4 - 1/12) =1/6

Hence, B alone can complete the work in 6 days.

Step-by-step explanation:

HOPE HELP