A and
B together can do a work
in 14 days when A work with 20%.
more efficiency & B work with 20% less
efficiency then together they
complete the whole work in
10 days
in how much time will A complete
the whole work?
Answers
Answered by
1
Step-by-step explanation:
wkjd5wyghbdkvx
ljdlhzj
Answered by
9
Step-by-step explanation:
A : B
6/5 : 4/5
6 : 4
3 : 2
work =14 ×5
= 70
5×10 =50W
A = 70/3 days