A and B together can finish a piece of work in 12 days. If 'A' alone can finish the same
work in 20 days, in how many days B alone can finish it?
Answers
Answered by
0
Answer:
Both A and B can complete 1/12th work in one day
So A+B=1/12 in one day
A alone can complete 1/20 th work
A=1/20 in one day
Now B alone how much work can complete
(1/20)+B=1/12
B =(1/12)-(1/20)
L.C.M of 12 and 20 is 60
So B=( (5–3)/60)
B=2/60=1/30
So alone can complete 1/30th work in one day
B alone can complete the work in 30 days
hope it helps u..
Answered by
0
Step-by-step explanation:
A+B 1 day work = 1/12
A' s 1 day work = 1/20
B's 1 day work = 1/12- 1/20
L.C.M of 12&20 is 60
1/12-1/20= 1/30
Ans. B alone can finish the work in 30 days.