A and B together can finish a piece of work in 12 days. IfA' alone can finish the same
work in 20days, in how many days Balone can finish
?​

Answers

Answered by johnwick97
5

Answer:

30 days

Step-by-step explanation:

A 1 day work = 1/20

A+B 1 day work = 1/12

B 1 day work = A+B 1 day work - A 1 day work

= 1/12 - 1/20

=5-3/60 = 2/60 = 1/30

B can finish work in 30 days

Answered by sawnitu2002gmailcom
1

Answer:

30 days

Step-by-step explanation:

A 1days work =1/20

A+B 1day work =1/12

B 1day work =A+B 1day work-A1 day work

=1/12-1/20

=5-3/60=2/60=1/30

B can finish work in 30 days.