A and B together can finish a piece of work in 16 days. A having worked for 8 days, B finishes the remaining work in 32 days. In how many days shall B finish the whole work alone?
Answers
Answered by
28
Solution :
A and B together can finish a piece of work in 16 days. A having worked for 8 days, B finishes the remaining work alone in 32 days.
The days shall be B finish the whole work alone.
Let A's work in 1 day = r
Let B's work in 1 day = m
We know that total work = 1
A/q
&
Thus;
The B's finish the whole work alone in = 48 days .
Answered by
68
Solution :- (in Simplest way).
Given That, A and B together can finish a piece of work in 16 days.
So,
→ Per day work of (A + B) = (1/16) --------- Equation (1).
Now,
Given That, A worked for 8 days , and B finishes Remaining work in 32 days.
we know That, Total work is 1.
So,
→ 8A + 32B = 1
→ 8A + 8B + 24B = 1
→ 8(A + B) + 24B = 1
Putting value of Equation (1) here , we get,
→ 8 * (1/16) + 24B = 1
→ (1/2) + 24B = 1
→ 24B = 1 - 1/2
→ 24B = 1/2
→ B = 1/(2*24)
→ B = 1/48 . = 48 days.
Hence, B alone can finish The Total work in 48 days.
Similar questions