A and B together can finish a piece of work in 30 days. They worked together for 20
days and then A left. After another 20 days, B finished the remaining work. In how
many days B. alone can finish the piece of work?
Answers
Answered by
1
Answer:
60 days
Step-by-step explanation:
According to question
A+B complete work in 30 days
Take L.C.M of (A+B)'s time to calculate the total work Assume total work 30 units
Hence,
(A+B)'s work/day = 1 Unit/day
(A+B)'s 20 day's work = 20x1 unit/day = 20 units
Rest work = 30−20=10 units
Now, Rest work done by A in 20 days
Then one day's work of A =1020=12
Total work done by A in=3012=60days