Math, asked by harsha0101, 1 year ago

A and B together can finish a piece of workin 12 days if a alone can finish the same work in 20 days in how many days B alone can finish it

Answers

Answered by TooFree
10

A and B can finish the work in 12 days

⇒ 1 day = 1/12 of the work


A can finish the work in 20 days

⇒ 1 day = 1/20 of the work


Calculate the amount of work B can do in a day:

1 day = 1/12 - 1/20 = 1/30


Find the number of days B needed to complete the work:

1/30 of the work = 1 day

30/30 of the work = 1 x 30 = 30 days


Answer: B will need 30 days if he worked alone.


siddhartharao77: :-)
Answered by Anonymous
2
 \huge {\bold {Solutions :-}}

____________________________________
Q: A and B together can finish a piece of workin 12 days if a alone can finish the same work in 20 days in how many days B alone can finish it ?
____________________________________


A and B do a work in 12 days

(A and B) 's one day work = 1/12

A alone do a work in 20

A' s one day work = 1/20


Now,

B' s one day work =

(1/12) - (1/20)
= (5 - 3)/60
= 2/60
= 1/30


Hence,

 \bold {\underline {B~alone~can~finish~it~in~30~days}}