A and B together can finish a work in 12 days.A can finish the same work in 20 days.In how many days B can finish the same work.
Answers
Answered by
1
in 12 day (A+B) can do a work
hence (A+B) 1 days work =1/12
similarly a's 1 day work =1/20
hence b's alone work= 1/12-1/20=2/60=1/30
hence b can finish his work in1/1/30= 30 days
hence (A+B) 1 days work =1/12
similarly a's 1 day work =1/20
hence b's alone work= 1/12-1/20=2/60=1/30
hence b can finish his work in1/1/30= 30 days
Answered by
1
1/A + 1/B = 1/C
A does work in A days, So per day A does 1/A amount
B does in B days, So per day B does 1/B amount
AB together they can do each day 1/A + 1/B this is equal to 1/12
=> 1/12 = 1/20 + 1/B solve to get B = 30 days
A does work in A days, So per day A does 1/A amount
B does in B days, So per day B does 1/B amount
AB together they can do each day 1/A + 1/B this is equal to 1/12
=> 1/12 = 1/20 + 1/B solve to get B = 30 days