A and B together can finish a work in 12 days, B&C in 24 days, C&A in 36 days. In how many days B alone
Can finish the work?
Answers
Answered by
0
Answer:
the B can finish there work in 18 days
Answered by
1
A and B can do (1/18)th of the work in a day.
B and C can do (1/24)th of the work in a day.
A and C can do (1/36)th of the work in a day.
2A+2B+2C = (1/18)+(1/24)+(1/36)
= (4/72)+(3/72)+(2/72)
= (9/72)
or
A+B+C = (9/144) = (1/16)th of the work in a day.
C alone does (1/16)-(1/18) = (18–16)/(16*18) = 2/(16*18) = (1/144)th part of the work in a day. So C, working alone, will complete the work in 144 days.