A and B together can finish a work in 12days if A alone can finish the same work in 20days in how many days B alone can finish it​

Answers

Answered by eshwaripatil
2

Answer:

B will complete the work in 30 days

Step-by-step explanation:

A alone can finish the same work in 20 days

means A does 1/20 th work per day

when both complete the work in 12 days

A completes 12 /20 th work in 12 days

So the work done by B = 1 - 12 /20 = 8/20 = 2/5

Therefore

in on day B will complete( 2 /5 ) ÷12 = 2/60 = 1/30

So B will complete the work in 1 ÷ 1/30 = 30 days