Math, asked by albannongrum1147, 10 months ago

A and B together can finish a work in 30 days. They worked for it for 20 days and then B left the work. The remaining work was done by A alone in 20 days more. In how many days can A alone finish the work?

A) 48 days B) 50 days C) 54 days D) 60 days

Answers

Answered by priyasandeep90909090
46

Answer:

answer D) 60 days

Step-by-step explanation:

Work done by A and B together in 1 day = 1/30

A + B = 1/30 => B = 1/30 - A

A and B worked together for 20 days + A alone completed the remaining work in 20 days = whole work

(A + B )20 + (A )20 = 1

40A + 20( 1/30 – A) = 1

20A = 1 – 20/30

20A = 10/30

A = 1/60

A alone can finish the work in 60 days.

Answered by BrainlyRaaz
105

Given :

  • A and B can complete work together = 30 days
  • They worked for it for 20 days and then B left the work.
  • The remaining work was done by A alone in 20 days more.

To find :

  • No. of days A alone can finish the work =?

Step-by-step explanation :

A and B can work together = 30 days.

But A and B worked together for 20 days.

Total Work = L. C. M of 30, 20 = 60 unit

So, A and B work together,

60 units = 30 days

? = 20 days

So, 60 × 20/30 = 40 unit

Now,

We got that A and B take 20 days to complete 40 units.

A alone take 20 day's to complete 20 units,

= 1 unit /1 day

Therefore, 60 unit = 1 × 60 = 60 days.

Hence,

No. of days A alone can finish the work = 60 day's.

Option d). 60 day's is the correct option.

Similar questions