Math, asked by deads3085, 6 hours ago

A and B together complete a task in 24 days, Cand B together complete the same task in 18 days, and A and C together complete the task in 12 days. How many days willAtake to complete the task ifhe works alone?​

Answers

Answered by 2008gargikgupta
0

123 I am not able to join the English reinforcement class of the tree of Life sciences and technology University admission test result published the blogpost I am not able to join

Answered by anshsingh79556
0

Answer:

A and B together do (1/14)th of the task in

1 day.

B and C together do (1/8)th of the task in 1

day.

A and C together do (1/7)th of the task in 1

day.

Adding all the three we get

2A+2B+2C do (1/14)+(1/8)+(1/7) =

(56+98+112)/784 = 266/784-133/392, or

A+B+C = 133/784 = 19/112

C does (19/112)-(1/14) = (19–8)/112 = 11/112th

of the work in 1 day.

A does (19/112)-(1/8) = (19–14)/112 = 5/112thof the work in 1 day.

B does (19/112)-(1/7) = (19–16)/112 = 3/112th

of the work in 1 day.

The least efficient person is B, who will

do the task, alone, in 112/3 or 37.33 days.

Next is A, who will do the task, alone, in

112/5 or 22.4 days.

C, the most efficient, will do the task,

alone, in 112/11 or 10.18 days.