A and b together complets a work in 4 days. A alone takes 6days. How many days will b alone take
Answers
Answered by
6
Refer to the attachment
as ur question is and b together complets a work in 4 days. A alone takes 6days. How many days will b alone take. so ans is
Hope it helps u ,⭐⭐⭐☺☺