A and B together finish a work in 30 days .They worked on it for 20 days and then B left. The remaining work was done by A alone in 20 days. A alone can finish a work in how many days?
Answers
Answered by
2
A+B= 20/30
so work done by A and B. is 2/3
now remaining work is 1/3
1/3 work is completed by A in 20 days
so A alone will complete the work in 60 days