A and B work together but A leaves the
job after 2 days. How much of the work
is still left?
Answers
Answered by
5
Answer:
1/3 part of work is completed by A in two days; Hence, one day's work of A = 1/6; Then, one day's work of B = 1/3-1/6=1/6; So, B alone can complete the whole work in 6 days
Step-by-step explanation: