A and b work together can do work in 8 days, b and c together in 6 days, while c and a together in 10 days.If they all work together, the work will be completed in
Answers
Answered by
0
Answer: 12 days
Step-by-step explanation:
A+B=8
B+C=6
C+A=10
A2+B2+C2=8+6+10=24
Then divide by 2
=A+B+C=12