A and b working separately can do a piece of work in 9 and 12 days respectively. if they work for a day alternately, a beginning, in how many days, the work will be completed?
Answers
Answered by
4
Solution :
_____________________________________________________________
Given :
A & B working separately can do a piece of work in 9 days & 12 days respectively.
_____________________________________________________________
To find :
If they work for a day alternatively they the time taken to complete the piece of work.
_____________________________________________________________
If A takes 9 days to complete the piece of work,.
The amount of work completed in 1 day = th of total work,.
___________________________
If B takes 12 days to complete the pice of work,.
Similarly,.
The amount of work completed in 1 day =
_____________________________________________________________
If they work alternatively, with A as begining,
Then,
Hence, the number of days be 2x+1,.
Then, the days that A work = x + 1 days
The days that B works = x days
Then,
⇒
⇒
⇒
⇒
⇒
⇒ 7x = 36 - 4
⇒ 7x = 32
⇒ x ≈ 5 days,.
The total number of days = 2x + 1
⇒ 2(5) + 1
⇒ 10 + 1
⇒ 11 days,.
_____________________________________________________________
Hope it Helps!!
⇒ Mark as Brainliest,.
_____________________________________________________________
Given :
A & B working separately can do a piece of work in 9 days & 12 days respectively.
_____________________________________________________________
To find :
If they work for a day alternatively they the time taken to complete the piece of work.
_____________________________________________________________
If A takes 9 days to complete the piece of work,.
The amount of work completed in 1 day = th of total work,.
___________________________
If B takes 12 days to complete the pice of work,.
Similarly,.
The amount of work completed in 1 day =
_____________________________________________________________
If they work alternatively, with A as begining,
Then,
Hence, the number of days be 2x+1,.
Then, the days that A work = x + 1 days
The days that B works = x days
Then,
⇒
⇒
⇒
⇒
⇒
⇒ 7x = 36 - 4
⇒ 7x = 32
⇒ x ≈ 5 days,.
The total number of days = 2x + 1
⇒ 2(5) + 1
⇒ 10 + 1
⇒ 11 days,.
_____________________________________________________________
Hope it Helps!!
⇒ Mark as Brainliest,.
Similar questions