A and B working separately can do a work in 5 days and 7 days respectively. If B starts the work
and they work on alternate days. In how many days will the work be completed?
Answers
Answered by
0
By B the work will complete in (2×7)+1=15 days
and By A work WILL complete in (2×5)+1=11days
IF YOU LIKE THIS ANSWER MARK THIS AS A BRAINLIEST ANSWER