A and B working separately can do piece of work in 9 to 12 day respectively. if they work for a day alternately a starts the work in how many days will the work be conpleted
Answers
Answered by
1
Hey mate
Your answer :---
'A' can do a work in 9 days.
A's one day work = 1/9
'B' can do a work in 12 days
B's one day work = 1/12
Now,
(A and B) 's one day work = 1/9+1/12 = 4+3/36 = 7/36
Hence A and B can do a work in 36/7 = 5+1/7 days ans.
If it helps you mark me as brainlist
Thanks
Have a great day
Your answer :---
'A' can do a work in 9 days.
A's one day work = 1/9
'B' can do a work in 12 days
B's one day work = 1/12
Now,
(A and B) 's one day work = 1/9+1/12 = 4+3/36 = 7/36
Hence A and B can do a work in 36/7 = 5+1/7 days ans.
If it helps you mark me as brainlist
Thanks
Have a great day