Math, asked by dogra5977, 9 months ago

A and b working separately can finish a work in 12 and 18 days- respectively. If they work together for 5 days and then a goes away, in how many days will b complete the work?

Answers

Answered by leaguegame990
5

Answer:

Step-by-step explanation:

H hvyvyvyvyvhvhvhvhvhvhvvhvyvyvyvyvyvtvyctctctctcyvyvububuhvv

Answered by wifilethbridge
5

B can complete the remaining work in 5.5 days

Step-by-step explanation:

A can do work in days = 12

A's 1 day work =\frac{1}{12}

B can do work in days = 18

B's 1 day work =\frac{1}{18}

So, (A+B)'s 1 day work = \frac{1}{12}+\frac{1}{18}=\frac{5}{36}

(A+B)'s 5 day work =\frac{5}{36} \times 5 = \frac{25}{36}

Remaining work = 1- \frac{25}{36}=\frac{11}{36}

A left

So, B can do work in days = 18

So, B can do\frac{11}{36}work in days =18 \times \frac{11}{36} = 5.5

So, B can complete the remaining work in 5.5 days