Math, asked by mansiydv98, 7 months ago

A and B, working together can finish a piece of work in 6 days, while A alone can do it in
9 days. How much time will B alone take to finish it ?​

Answers

Answered by shounakb07
0

Answer:

3/2 days

Step-by-step explanation:

B will take 3/2 days..

I Think..