Math, asked by Myrasharma, 1 year ago

A and B working together can finish a piece of work in 6 days while a alone can do it in 9 days how much will be alone take to finish it?


sridevi77: hiii

Answers

Answered by sridevi77
4
ans= 18 days,b can complete the work in 18 days
Attachments:
Answered by ashutosh4228
2
a place which one day work is equal to 1 by 6 B can do it in 1 by 9 days 1 by 6 minus 1 by 9 is equal to 3 by 54 is equal to 18 days