Math, asked by pakhisaikia201, 24 days ago

A and B working together complete a work in 35 days. If A takes 60 days to complete it, how long would B alone take to complete is?

a) 72 days
b) 64 days
c) 81 days
d) 84 days ​

Answers

Answered by kumareshanixbsbk
0

Answer:

84

Step-by-step explanation:

Correct answer is option D 84 days

Answered by xxitscottoncandyxx57
0

Answer:

: 84 days

Step-by-step explanation:

work done by (A+B) in 1 day = 1/35

work done by A in 1 day = 1/60

work done by B = work done by (A+B) - work done by A

= 1/35-1/60

= __12-7__= 5/420 =1/84

420

therefore, time taken by B alone to complete the work = 84 days..

hope it's helpful..