A and B working together they can complete in 8 days and A alone can complete that work in 12 days then B alone can do that work in how many days

Answers

Answered by Lightningmequin
10
here is your answer.
Attachments:
Answered by Anonymous
3

Step-by-step explanation:

Please refer the attachment s then u will understand