Math, asked by Rangar6793, 1 year ago

A b & c can do a work i 4 days a lone does in 12 days b in 18 day

Answers

Answered by TooFree
5

A can do the work in 12 days

⇒ 1 day = 1/12 of the work


B can do the work in 18 days

⇒ 1 day = 1/18 of the work


A, B and C can do the work in 4 days

⇒1 day = 1/4


Find the time C needed if he works alone:

1 day = 1/4 - 1/8 - 1/12 = 1/24

1/24 of the work = 1 day

24/24 of the work = 1 x 24 = 24 days


Answer: C can do the work in 24 days

Answered by anujgupt
0
the correct answer is 24