A, B & C complete a work in 10, 12 & 15 days respectively. If they start the work together tillthe whole work gets completed. Find the share of A out of the total wages of Rs. 750?
Answers
Answered by
3
Answer:
A=1/10
B = 1/12
C= 1/15
take l.c.m of 10,22 and 15.. =60
then
A+B+C= 1/10+1/12+1/15
= 15/60
=4
now share of A = 6/15*750
=300