Math, asked by lipsykedia, 7 months ago

A B and C can complete a job by themselves in 10 days 15 days in 30 days respectively A and B start the work together but after 2 days B leaves the remaining work is then completed by a and see how long did a and c work together​

Answers

Answered by avaniphushkania
1

Answer:

In 7 days, the total work was completed

Solution:

Given that,

A, B and C can complete a work in 10, 12 and 15 days respectively

Given that,

After 2 days, A leaves the job

So, A worked for 2 days alone

Let "x" be the days in which total work was completed

B left the job 3 days before the work was completed

Therefore,

B worked for (x - 3) days

C completed the remaining work alone

Thus C worked for "x" days

Therefore,

\begin{gathered}\frac{2}{10} + \frac{x-3}{12} + \frac{x}{15} = 1\\\\Make\ the\ denominators\ same\\\\\frac{2 \times 6}{10 \times 6} + \frac{(x-3) \times 5}{12 \times 5} + \frac{x \times 4}{15 \times 4} = 1\\\\12 + 5x - 15 + 4x = 60\\\\9x - 3 = 60\\\\9x = 63\\\\x = 7\end{gathered}

10

2

+

12

x−3

+

15

x

=1

Make the denominators same

10×6

2×6

+

12×5

(x−3)×5

+

15×4

x×4

=1

12+5x−15+4x=60

9x−3=60

9x=63

x=7

Thus, in 7 days, the total work was completed

Answered by manishigangwar
0

Answer:

the time till when a and b will work together is 5 days.

Attachments:
Similar questions