A B and C can complete a job work individually in 10,20 and 60 days respectively if they were to get her in how many days will they complete the work
SD8:
please clarify the question
Answers
Answered by
7
Answer:
Step-by-step explanation:
daily capacity=total work/time to finish this work.
Each capacity 1/10, ..1/60 of doing work.
When all together to finish 1 work.
(1/10+1/20+1/60)*x days=1
After solving this x=6 days
Answered by
0
Answer:
A=1//10
B=1/20
C=1/60
so,
1/10+1/20+1/60
=6+3+1/60
1/6
....A+B+C can complete the work in 6 days
HOPE ITS HELPS YOU!