Math, asked by bhupigohil5052, 1 year ago

A, b and c can complete a piece of work in 24,8 and 16 days respectively. how many days they will complete the same work working together?

Answers

Answered by sibhiamar
0
A, B and C can complete a piece of work in 24,8 and 16 days respectively

so, A can complete a work in 24 days
A 's one day work = 1/24

so, B can complete a work in 8 days
B's one day work = 1/8

so, C can complete a work in 16 days
C 's one day work = 1/16

so, A, B and C (work together) one day work
= 1/24 + 1/8 + 1/16
= 1/8(1/3 + 1 + 1/2)
= 1/8((2+3+6)/6)
= 1/8(11/6)
= 11/48

so, no of days A, B and C whole work = 48/11 days = 4(4/11) days