A, B and C can complete a work in 10, 12 and 15 days respectively. All three of them starts together but after 2 days A leaves the job and B left the job 3 days before the work was completed. C completed the remaining work alone. In how many days was the total work completed?
A) 5 B) 6 C) 7 D) 8
Answers
Sᴏʟᴜᴛɪᴏɴ :-
→ LCM of 10,12 and 15 = 60units = Let Total work.
Than,
→ Efficiency of A = (Total work) / (Total Days) = (60/10) = 6 units/day.
→ Efficiency of B = (Total work) / (Total Days) = (60/12) = 5 units/day.
→ Efficiency of C = (Total work) / (Total Days) = (60/15) = 4 units/day.
Now, we have given that, all started work and after 2 days A leaves the job.
So,
We can say that, for first 2 days all three work together .
So,
→ in first 2 days all completed = 2(6 + 5 + 4) = 30 units of work.
____________
→ Left work now = 60 - 30 = 30 units.
Now, we have given that, B left the job 3 days before the work was completed.
So,
we can say that, As A already left, only C work alone for last three days.
Therefore,
→ C completed in last 3 days = 3 * 4 = 12 units .
_____________
→ Left work now = 30 - 12 = 18 units.
And, now, we can say that, As A already left, this was done by (B + C) together,
So,
→ No. of Days by (B+C) = 18/(5+4) = 18/9 = 2 Days.
______________
Hence,
→ Total Number of Days = 2(A + B + C) + 2(B + C) + 3(C) = 7 Days.(Ans.)